Bypass navigation and go to content
GO Train

Project Status Update

Updated: April 2, 2014

Notice of Completion of Environmental Project Report for the Electrification of Union Pearson (UP) Express: April 1, 2014 (pdf)

On December 3, 2013 Metrolinx issued the Notice of Commencement under the Transit Project Assessment Process (TPAP), in accordance with O. Reg. 231/08 for electrification of the UP Express.

Metrolinx has now completed the Environmental Project Report (EPR), which is being made available for public review and comment. Interested persons are encouraged to review this document and provide comments by April 30, 2014 to:

Karen Pitre
Executive Director, Electrification
Metrolinx-GO Transit
20 Bay Street, Suite 600
Toronto, ON M5J 2W3
tel: 416-874-5910
e-mail: Karen.Pitre@metrolinx.com

There are circumstances where the Minister of the Environment has the authority to require further consideration of the transit project, or impose conditions on it. These include if the Minister is of the opinion that:

  • The transit project may have a negative impact on a matter of provincial importance that relates to the natural environment or has cultural heritage value or interest: or,

  • The transit project may have a negative impact on a constitutionally protected Aboriginal or treaty right.

Before exercising the authority referred to above, the Minister is required to consider any written objections to the transit project that he or she may receive within 30 days after the Notice of Completion of the EPR is first published.  If you have discussed your issues with the proponent and you object to the project, you can provide a written submission to the Minister of the Environment by no later than April 30, 2014 to the address provided below. All submissions must clearly indicate that an objection is being submitted and describe any negative impacts to matters of provincial importance (natural/cultural environment) or Aboriginal rights.

Environmental Approvals Access and Service Integration Branch
Ministry the Environment
2 St. Clair Avenue West, Floor 12A
Toronto, ON M4V 1L5
Attention: Adam Sanzo, Project Officer
tel: 416-314-8001 / 1-800-461-6290
fax: 416-314-8452
e-mail: EAASIBGen@ontario.ca

To view the report, please click the links below:

Executive Summary
EPR Table of Contents and Glossary
EPR Chapter 1 – Introduction
EPR Chapter 2 – Assessment of Facility Locations
EPR Chapter 3 – Scope of the Project
EPR Chapter 4 – Baseline Conditions
EPR Chapter 5 – Detailed Project Description
EPR Chapter 6 – Impact Assessment & Monitoring
EPR Chapter 7 – Commitments & Future Work
EPR Chapter 8 – Consultation
EPR Chapter 9 – Approvals and Permits

EPR Appendices
Appendix A - Natural Environment Assessment Report
Appendix B - Land Use Assessment Report
Appendix C - Cultural Heritage Assessment Report
Appendix D - Stage 1 Archaeological Assessment Report
Appendix E - Air Quality Assessment Report
Appendix F - Noise and Vibration Assessment Report
Appendix G - Visual Impact Assessment Report
Appendix H - Electromagnetic Compatibility (EMC) Report
Appendix I - Traffic Report
Appendix J - Consultation Record
Appendix K - Utilities Report
Appendix L - Maintenance Facility Conceptual Design Report


January/February 2014 Public Open Houses: UP Express Electrification Environmental Assessment (EA)

As part of the Environmental Assessment (EA) process, Metrolinx and Hydro One held joint Public Open Houses in January/February 2014 to share a project update, and seek feedback on the following:

  • Overview of Preliminary Design for Union Pearson (UP) Express Electrification:
    • Traction Power Supply (Hydro One)
    • Traction Power Distribution
    • Maintenance Requirements
    • Construction Activities
  •  EA Studies (including potential environmental effects, mitigation measures)
  • Next Steps/Timelines

The update is summarized on the Public Open House display panels and on the Hydro One website.

 

Notice of Commencement (pdf)

Notice of Commencement

June 2013 Public Open Houses: UP Express Electrification Environmental Assessment (EA)

As part of the Environmental Assessment (EA) process, Metrolinx held a series of Public Open Houses in June 2013 to share a project update, and seek feedback on the following:

  • Overview of Conceptual Design for Union Pearson (UP) Express Electrification:
    • Traction Power Supply
    • Traction Power Distribution
    • Maintenance Requirements
  • Overview of EA Studies
  • Next Steps

The Project Scope, EA Process, Power Distribution, Study Areas, and more is outlined on the Public Open House display panels.
Comments and questions from the Public Open Houses (June 2013) have been compiled in a Summary Report.


June 2012 Public Meeting: Electrification Project Update

In June 2012 Metrolinx held a Public Meeting to share an Electrification project update:

  • Introduction of the Electrification Team
  • Overview of work completed to date:
    • Electrification Study
    • Metrolinx Recommendations
  • Obtain feedback on key issues and opportunities related to this work and consultation process
  • Next steps

For more information please see the presentation from this meeting.

Comments and questions from the Public Meeting (June 2012) have been compiled in a Summary Report and appendices.


    Electrification Performance Specifications: December 2012
    1 Electrification Performance Specifications: Executive Summary 9 Maintenance Facilities: Part 2
    2 Traction Power Supply System 10 SCADA System
    3 Traction Power Distribution System 11 Operations Control Centre
    4 Grounding and Bonding 12 System Integration
    5 Electromagnetic Compatibility 13 System Assurance
    6 Signal System Compatibility 14 Safety and Security
    7 Operations and Maintenance 15 Sustainability
    8 Maintenance Facilities: Part 1  


    Electrification Reports

    1 Traction Power System Modeling and Simulations

     
       

    Project Background

    Preliminary Design and Environmental Assessment

    Based on the 2010 Electrification Study, Metrolinx initiated the Environmental Assessment (EA) for electrification of the Union Pearson (UP) Express service from Union Station to Toronto Pearson International Airport. The proposed undertaking involves electrification of approximately 25km of track along the Union Station GO rail corridor and the Kitchener GO rail corridor, beginning west of the Union Station train shed to Highway 427, where the route then follows the new UP Express spur link to Terminal 1 (Toronto Pearson). The key map below shows the EA study area:

    Key Map

    The scope of the project includes engineering design of the electrical power supply and distribution for the UP Express service, including the following components:

    • Power Supply
    • Power Distribution
    • Maintenance Requirements

    Following the June 2013 Public Open Houses, additional design work was undertaken to confirm the traction power supply requirements related to electrifying UP Express. As a result, it was determined that only one transformer station will be required in the vicinity of the existing Richview Hydro One substation located at the southeast corner of Highway 27 and Dixon Road (see key map above). The new transformer station will be supplied from the Hydro One network.

    Overview of TPAP Process

    Metrolinx and Hydro One are proposing to carry out an Integrated EA process in order to satisfy both Metrolinx’s requirements under the Transit Project Assessment Process (TPAP) (O. Reg. 231/08) as well as Hydro One’s requirements under the Class EA for Minor Transmission Facilities (Class EA). The graphic below illustrates the Integrated EA process steps.

    TPAP Process

    Electrification Study: Findings and Final Report

    On May 26, 2009, Metrolinx announced that it would be undertaking a one-year study on the feasibility of electrification of the entire GO rail system. In comparison to other similar studies, this study was unique as it examined the entire GO rail system. It was comprehensive in its approach and addressed the impact of different technologies at a high level of detail. The Study considered the economic, social, environmental, health, and technological factors for current and future diesel and electric technologies. The study was completed in December 2010.

    On January 19, 2011, Metrolinx released the findings of its comprehensive study on the electrification of the entire GO Transit rail system and the future Air Rail Link (ARL), as a future alternative to Tier-4 diesel trains.

    After a careful review of the findings, the staff recommended to the Metrolinx Board of Directors to proceed with the electrification of the GO Kitchener (formerly) Georgetown and Lakeshore corridors in phases, beginning with the ARL on the Kitchener corridor. At its Board meeting on January 26, 2011, the Metrolinx Board of Directors approved the staff recommendation, subject to provincial funding. The Province of Ontario, through the Ministry of Transportation, has funded the environmental assessment for Phase 1: the Air Rail Link from Union Station to Pearson Airport as a first step toward electrification.

    Reference Materials

    Shortly after Metrolinx announced that it would undertake a comprehensive study of the electrification of the entire GO Transit rail system, the Metrolinx Board of Directors established a Community Advisory Committee (CAC) to assist in developing the Terms of Reference for the study.

    The CAC provided substantive advice to Metrolinx, helping to shape the Terms of Reference for the Electrification Study. The CAC, whose mandate was complete once the Terms of Reference were developed, consisted of a diverse group of transit and engineering experts, community leaders, GO Transit riders, and urban planners. Members of the former CAC have been invited to continue their participation as the Electrification Study continues.

     

    The Big Move

    GOTrain

     

    In late 2008, Metrolinx published a Regional Transportation Plan The Big Move a multimodal vision for regional transportation to strengthen the economic, social and environmental sustainability of the Greater Toronto and Hamilton Area. The Big Move sets out a fast, frequent and expanded regional rapid transit network as a key element of the plan. The plan includes establishing Express Rail and Regional Rail services at speeds and frequencies that could be enhanced by system electrification.

     

    Questions and/or comments are welcomed by Metrolinx at any time, you can reach the Electrification Project by email at electrification@metrolinx.com
     


Contact Us

Karen Pitre
Executive Director, Electrification
20 Bay Street, Suite 600
Toronto, Ontario, Canada
M5J 2W3

Tel.: 416.874.5910
E-mail: electrification@metrolinx.com

For a list of other GO Transit contacts, please visit Contact GO on gotransit.com