Bypass navigation and go to content
Galt Sub looking West

Central Corridor Bridges

The Central Corridor Bridges work package involves widening four railway bridges in the central portion of the Georgetown South corridor: Black Creek/Black Creek Drive, Eglinton Avenue and Ray Avenue.

Updates

  • April 30 – This month, we completed the widening of one pier and prepared the two abutments with shoring to protect the tracks while we excavate. A second shrouded pile driver is on site to start work on widening one of the abutments. The shrouds were built for this project to reduce noise levels. Noise and vibration monitors are set up along the project area and results are posted online every week. Almost all of the H-piles are expected to be installed by the end of the summer.
  • April 13 – We are widening six piers and two abutments to hold additional tracks for expanded GO Transit service. A second shrouded impact hammer will start operating later in April. Regular construction hours now include Saturday work between 9 a.m. – 7 p.m. Weekend hours are necessary because some of the work must be done when trains are not operating. View the Construction Update.

Black Creek/Black Creek Drive

Project Schedule

  • Design complete: Spring 2011
  • Construction start: Fall 2011
  • Construction complete: 2013

What we are doing

  • Widening the bridges over Black Creek and Black Creek Drive to accomodate three additional sets of tracks
    • These new tracks are required to expand GO Transit service and the new Air Rail Link service

How this will affect you

  • Lane restrictions during construction (please check the update section for current restrictions)
  • This project requires the installation of piles and shoring to create the foundation to support the bridges. Piles are necessary to reach deep into the ground to find soil conditions capable of supporting extra weight from the additional tracks. Installation methods will include shrouded impact hammer and augering. Nearby residents can expect to hear noise and feel vibration during installation. The shrouds will help reduce the noise.

Noise and Vibration

Noise and vibration monitors have been set up along the Black Creek/Black Creek Drive project area to monitor any noise and vibration generated by the construction. This data will be posted on a weekly basis.

The following graph displays 1-hour averaged noise levels measured in decibels (dbA).

Central Bridges Noise Monitoring Graph

For a map of the station locations, please click here.

Archived graphs

2011 | January 2-March 31 | April 2-7 | April 9-14 | April 16-21

Vibration

No elevated vibration levels were recorded during this construction period.

To learn more about how we're monitoring noise and vibration during construction, please see our Noise and Vibration page.

Tenders

Design consultant: Aecom
Construction contractor: Dufferin Construction Company

Community Updates

 

Eglinton Avenue

Project Schedule

  • Design complete: Spring 2012
  • Construction start: Spring 2013
  • Construction complete: Summer 2014

What we are doing

  • Widening bridges to accommodate more tracks

How this will affect you

  • Some partial and full road closures during construction
    • Will work to limit full closures to nights and weekends
  • Limited noise and vibration

Noise and Vibration

  • There will be some noise and vibration due to the construction, but we will use construction methods to minimize these impacts
  • Noise and vibration will be monitored and reported during construction

Tenders

Design consultant: Aecom
Construction contractor: Not Yet Awarded

Community Updates

For updates from 2010 or 2011, please see our Communication Materials page.

 

Ray Avenue

Project Schedule

  • Design complete: Spring 2012
  • Construction start: Spring 2013
  • Construction complete: Summer 2014

What we are doing

  • Widening bridges to accommodate more tracks

How this will affect you

  • Some partial and full road closures during construction
    • Will work to limit full closures to nights and weekends
  • Limited noise and vibration

Noise and Vibration

  • There will be some noise and vibration due to the construction, but we will use construction methods to minimize these impacts
  • Noise and vibration will be monitored and reported during construction

Tenders

Design consultant: Aecom
Construction contractor: Not Yet Awarded

Community Updates

For updates from 2010 or 2011, please see our Communication Materials page.

For more information on the Central Corridor Bridges, please contact Kelly at 416-604-9582.

How are we doing?

How are we doing?

Tell us what you think of our communications, our public meetings and the information we provide.
Learn more...

Stay in the Know!

Sign up to receive email updates on project information. Subscribe now!

Event Calendar

Check out our Event Calendar to view information about upcoming events.
Find out more...

Contact Us

Georgetown South Project
20 Bay Street, Suite 600
Toronto, ON M5J 2W3
416-406-0489
gts@gotransit.com

Strachan Community Office
901 King Street West, Suite 102
Toronto, ON M5V 3H5
416-581-1300

Weston Community Office
1631 Weston Road
Toronto, ON M9N 1T8
416-241-2300

WTD Community Office
18 Hook Avenue, Suite 204
Toronto, ON M6P 1T4
416-604-9582
By appointment only