Denison Road Underpass

The new Denison Road will pass under the tracks and be re-aligned between Jane Street and Weston Road. The existing Denison Road East will be converted into a cul-de-sac, as will Sam Frustaglio Drive. Arthur Street will become a turn-about.

Updates

  • April 30 – The first half of the GO bridge deck was poured over the weekend of April 14. Sheet piling work has also begun to the west of the tracks between Weston Road and the rail crossing. Sheet piles are interconnected steel plates that are inserted into the ground with vibratory equipment, and will form the basis of the retaining walls for the future lowered Denison Road. The installation of this section of sheet piling work is scheduled to be completed by the end of May. The track grading work has been completed and ballast will be laid on May 11. The entire GO bridge structure will be completed by the end of May. The cut-over for GO tracks will take place from May 11 to 13 and for CP Rail tracks from May 29 to 31 in order for work to begin on the CP Rail bridge.
  • April 11 – Beginning Monday, April 16, sewer work will begin in the intersection of Denison and Weston Roads. Traffic travelling north and south on Weston Road will be reduced to one lane in either direction. Bus stops for TTC will be relocated; bus service will not be impacted.

Project Schedule

  • Utility relocation start: January 2011
  • Construction start: Spring 2011
  • Construction complete: Spring 2013

What we are doing

  • Utility relocation – which includes moving city services such as gas and hydro – will take place before major construction can begin
  • Pre-construction condition inspections have begun for properties within 100 metres of the construction area. The Weston Community Office has been in touch with those in the area to provide advance notice.
  • May 16, 2011 – Sewer and water main work will being on Denison Road East – to be completed September 2011.
  • Track shift work Friday June 17, 2011 at 7 a.m. to Monday June 20, 2011 at 7 a.m.
    • Tracks will be shifting north east towards CP

How this will affect you

  • The majority of the work will take place during regular construction hours.
  • Some construction work may be required outside these hours. Advance notice will be provided to the surrounding community when are working outside the regular hours.
  • Denison Road will be closed between Jane Street and Weston Road for a minimum of one year during construction
    • a signalized pedestrian crossing will be maintained at all times
    • there will be minimal impact to Weston Road
  • Road closure starts April 26, 2011 until spring 2013
  • Sewer and Water Main Work, May 16, 2011 to September 2011:
    • One lane way will remain open on Denison Road East to allow passage of vehicles
    • No driveways or building access will be blocked
    • Side walk on south side of Denison Road East will not be accessible, north side will
    • Weston Road at Denison will see lane restrictions
    • TTC bus stops will be temporarily relocated – bus service will continue as normal
    • 48 hours advance notice provided for any service interruptions
  • Heavy construction work will take place June 18 and June 19, 2011, which will include:
    • Tamping of soil and laying of crushed stone as ballast
    • Vibration
  • Night work will be lighter construction using cranes and trucks:
    • Noise from trucks reversing will be heard
    • Lighting will be needed to maintain visibility

Noise and Vibration

Noise and vibration monitors have been set up along the Denison Road Underpass project area to monitor any noise and vibration generated by the construction. This data will be posted on a weekly basis.

The following graph displays 1-hour averaged noise levels measured in decibels (dbA).

Denison Road Underpass Noise Monitoring Graph

For a map of the station locations, please click here.

Archived graphs

2011 | January 2-April 2 | April 2-9 | April 9-16

Vibration

No elevated vibration levels were recorded during this construction period.

To learn more about how we're monitoring noise and vibration during construction, please see our Noise and Vibration page.

Tenders

Design consultant: R.V. Anderson
Construction contractor: Dufferin Construction Company

Community Updates

For more information on the Denison Road Underpass, please contact the Weston Community Office at 416-241-2300.

How are we doing?

How are we doing?

Tell us what you think of our communications, our public meetings and the information we provide.
Learn more...

Stay in the Know!

Sign up to receive email updates on project information. Subscribe now!

Event Calendar

Check out our Event Calendar to view information about upcoming events.
Find out more...

Contact Us

Georgetown South Project
20 Bay Street, Suite 600
Toronto, ON M5J 2W3
416-406-0489
gts@gotransit.com

Strachan Community Office
901 King Street West, Suite 102
Toronto, ON M5V 3H5
416-581-1300

Weston Community Office
1631 Weston Road
Toronto, ON M9N 1T8
416-241-2300

WTD Community Office
18 Hook Avenue, Suite 204
Toronto, ON M6P 1T4
416-604-9582
By appointment only