Bypass navigation and go to content
Galt Sub looking West

Strachan Avenue Overpass

The Strachan Avenue Overpass is one of the grade separations for the Georgetown South Project. Strachan Avenue will be raised by, at most, 2 metres to pass over the rail corridor. In turn, the rail corridor will be lowered from Bathurst Street to King Street West, the lowest point of up to 8 metres below at Strachan Avenue. The new overpass will also accommodate bicycle lanes and sidewalks.

Updates

  • May 16 – We are beginning construction of a retaining wall on the property next to Strachan Avenue and just north of East Liberty Street. Beginning May 22, 2012, Western Battery Road will be closed at the bend for approximately three weeks. See the construction update.
  • May 15 – There will be overnight and weekend work for the Strachan Avenue Overpass from Tuesday, May 15 to Monday, May 21. See the construction update.
  • May 15 – Enbridge Inc. is relocating their gas main that runs across the tracks at Strachan Avenue in order to accommodate work for the Strachan Avenue Overpass. This work will require lane restrictions on Wellington Street at Strachan Avenue for approximately two weeks. See the construction update.

Project Schedule

  • Phase 1 construction begins: winter 2011
  • Phase 2 construction begins: summer 2011
  • Siphon Tunnel complete: summer 2012
  • Caisson drilling for retaining walls
    • Middle wall (not including bridge section) complete: mid to late May 2012
    • North wall (not including bridge section) complete: early June 2012
    • Middle and north walls (bridge section) begins: fall 2012
    • South wall begins: spring 2013
  • Temporary realignment of Strachan Avenue
    • Construction begins: spring 2012
    • Construction complete: late 2012
    • In effect from late 2012 to early 2014
  • Phase 2 construction complete: fall 2014

What we are doing

Phase 1 of the work will include:

  • construction of a retaining wall in the north-east quadrant, which will also support the City of Toronto’s Fort York Pedestrian Bridge
  • utility work, including the construction of a new utility tunnel

Phase 2 of the work will include:

  • Construction of the Storm Water Siphon Tunnel
    • Currently, a 3-metre diameter storm sewer runs directly underneath Strachan Avenue and needs to be located below the future lowered rail corridor
    • Work on the vertical shafts for the new sewer (siphon tunnel) will start at the southeast corner of Strachan Avenue and Fleet Street and the southwest corner of Strachan Avenue and Douro Street
  • Construction of the Retaining Walls
    • Three retaining walls will be required to support the lowered rail corridor: a north, centre and south wall
    • Construction will begin on the north and centre walls by augering (drilling) concrete piles
  • Temporary realignment of Strachan Avenue
    • Strachan Avenue will be diverted to the west to facilitate construction of the lowered rail corridor
  • Excavation of the rail corridor begins
    • The corridor will be excavated in two phases to maintain railway operations
    • The north section of the corridor will be excavated first with all rail service shifted to the south tracks

How this will affect you

  • The majority of the work will take place during regular construction hours
  • Some construction work may be required outside these hours
  • Advance notice will be provided to the surrounding community when are working outside the regular hours
  • Temporary realignment of Strachan Avenue in 2012
  • Short-term road closure at Strachan Avenue may be needed in 2012 and/or 2013

Photos and Renderings

Strachan Avenue Overpass Rendering Looking East Strachan Avenue Overpass Rendering From Above Strachan Avenue Overpass Rendering Looking West August 18, 2011 – Strachan Avenue Overpass Construction October 17, 2011 – Strachan Avenue Overpass Construction November 21, 2011 – Strachan Avenue Overpass Construction January 9, 2012 – Strachan Avenue Overpass Construction January 27, 2012 – Strachan Avenue Overpass Construction January 27, 2012 – Strachan Avenue Overpass Construction March 6, 2012 – The Tunnel Boring Machine (TBM) in action.

 

Noise and Vibration

Noise and vibration monitors have been set up along the Strachan Avenue Overpass project area to monitor any noise and vibration generated by the construction. This data will be posted on a weekly basis.

The following graph displays 1-hour averaged noise levels measured in decibels (dbA).

Strachan Avenue Overpass Noise Monitoring Graph

For a map of the station locations, please click here.

Archived graphs

2011 | January 2-March 31 | April 2-7 | April 9-14 | April 16-21

Vibration

No elevated vibration levels were recorded during this construction period.

To learn more about how we're monitoring noise and vibration during construction, please see our Noise and Vibration page.

Tenders

Design consultant: AECOM
Construction contractor: Phase 1: Kenaidan Contractors
Construction contractor: Phase 2: EllisDon

Community Updates

For more information on the Strachan Avenue Overpass, please contact the Strachan Community Office at 416-581-1300.

How are we doing?

How are we doing?

Tell us what you think of our communications, our public meetings and the information we provide.
Learn more...

Stay in the Know!

Sign up to receive email updates on project information. Subscribe now!

Event Calendar

Check out our Event Calendar to view information about upcoming events.
Find out more...

Contact Us

Georgetown South Project
20 Bay Street, Suite 600
Toronto, ON M5J 2W3
416-406-0489
gts@gotransit.com

Strachan Community Office
901 King Street West, Suite 102
Toronto, ON M5V 3H5
416-581-1300

Weston Community Office
1631 Weston Road
Toronto, ON M9N 1T8
416-241-2300

WTD Community Office
18 Hook Avenue, Suite 204
Toronto, ON M6P 1T4
416-604-9582
By appointment only