Strachan Avenue Overpass

The Strachan Avenue Overpass is one of the grade separations for the Georgetown South Project. Formerly a level crossing, Strachan Avenue has been raised and the rail corridor lowered several metres. In October 2013, trains began operating on new tracks in a new north lowered corridor and the level crossing was removed. A year later, the new Strachan Avenue bridge fully opened providing two lanes for vehicles, two lanes for cyclist and two sidewalks over the rail corridor. 

Updates

  • January 28, 2015 – There will be overnight track work between 7 p.m. and 5 a.m., as needed, throughout the month of February. This work includes completing the welding and de-stressing of new track, as well as bringing the new King Street West signal bridge online. This work can only be completed when trains are not operating.
  • January 26, 2015 – Starting end of January until end of February (may be rescheduled due to weather) we will be reconstructing the sidewalk at the northwest corner of Strachan Ave. and East Liberty St. This work will reconfigure the slope of the sidewalk.
  • January 9, 2015 – Starting Monday, January 12, until the end of the month, we will be welding track in the lowered rail corridor between 7 p.m. and 5 a.m. This work can only be completed at night when the trains are not operating. This work is to remove track joints creating continuously welded rail which reduces noise from train wheels crossing over the joints.
Strachan Avenue Overpass Rendering Looking West Strachan Avenue Overpass Rendering Looking East Strachan Avenue Overpass Rendering Looking East Strachan Avenue Overpass Rendering Closeup Looking West Strachan Avenue Overpass Rendering Closeup Strachan Avenue Overpass Rendering

 

Project Schedule

  • Phase 1 construction started: winter 2011
  • Phase 1 construction completed: spring 2012
  • Phase 2 construction started: summer 2011
  • Phase 2 construction complete: end of 2014

What we are doing

  • Utility relocation
    • Construction of a siphon tunnel, utility tunnel, and relocation of all utilities
  • Construction of three retaining walls to support the lowered rail corridor: a north, centre and south wall
  • Excavation of the rail corridor
    • The corridor is being excavated in two phases to maintain railway operations
    • The north section of the corridor was excavated first with all rail service being shifted to the south tracks
    • After the north corridor excavation was complete, train operations shifted to this lowered corridor (project milestone), and excavation began in the south corridor
  • Installation of struts and the permanent Strachan Avenue bridge

How this will affect you

  • Temporary realignment of Strachan Avenue
  • There is a temporary loss of parking spots (south side of Douro Street near Strachan Avenue, Western Battery Road)
  • Occasional lane restrictions
  • Removal of the level crossing

Photos (2014)

Photos (2011-2013)

Noise and Vibration

Noise and vibration monitors have been set up along the Strachan Avenue Overpass project area to monitor any noise and vibration generated by the construction. This data will be posted on a weekly basis.

The following graph displays 1-hour averaged noise levels measured in decibels (dbA).

Strachan Avenue Overpass Noise Monitoring Graph

For a map of the station locations, please click here.

Archived graphs

2011 | 2012 | 2013 | December 30, 2013-January 4, 2014 | January 6-11 | January 13-18 | January 20-25 | January 27-February 1 | February 3-8 | February 10-15 | February 17-22 | February 24-March 1 | March 3-8 | March 10-15 | March 17-22 | March 24-29 | March 31-April 5 | April 7-12 | April 14-19 | April 21-26 | April 28 - May 3 | May 5-10 | May 12-17 | May 19-24 | May 26-31 | June 2-6 | June 9-14 | June 16-21 | June 23-28 | June 30-July 5 | July 7-12 | July 14-19 | July 21-26 | July 28-August 2 | August 4-9 | August 11-16 | August 18-23 | August 25-30 | September 1-6 | September 8-13 | September 15-20 | September 22-27 | September 29-October 4 | October 6-11 | October 13-18 | October 20-25 | October 27-November 1 | November 3-8 | November 10-15 | November 17-22 | November 24-29 | December 1-6 | December 8-13 | December 15-20 | December 22-27 | December 29-January 3

Vibration

No elevated vibration levels were recorded during this construction period.

To learn more about how we're monitoring noise and vibration during construction, please see our Noise and Vibration page.

Tenders

Design consultant: AECOM
Construction contractor: Phase 1: Kenaidan Contractors
Construction contractor: Phase 2: EllisDon

Community Updates

For updates from 2010 or 2011, please see our Communication Materials page.

For more information on the Strachan Avenue Overpass, please contact the Strachan Community Office at 416-581-1300.