West Corridor Bridges

The West Corridor Bridges work package involves widening for railway bridges in the western portion of the Georgetown South corridor: Kipling Avenue, Martin Grove Road, Highway 27 and Highway 427.

Updates

  • April 30 – At Highway 427, work on constructing a retaining wall under the bridge continues with the placement of formwork and rebar. We are pouring concrete for the retaining wall facing in sections where the formwork and rebar have already been placed. Once the concrete is strong enough, the formwork will be removed.
    This work is expected to be complete by the summer. Phase 2 of the West Corridor Bridge package – which involves widening the bridges at Kipling Avenue, Martin Grove Road and Highway 27 – is expected to start in the summer.

Kipling Avenue

Project Schedule

  • Design and community consultation to begin soon

What we are doing

  • Add new spans to existing bridge to accommodate more tracks

Noise and Vibration

  • There will be some noise and vibration due to the construction, but we will use construction methods to minimize these impacts
  • Noise and vibration will be monitored and reported during construction

Tenders

Design consultant: Stantec Consultingd
Construction contractor: Not Yet Awarded

 

Martin Grove Road

Project Schedule

  • Design and community consultation to begin soon

What we are doing

  • Add new spans to existing bridge to accommodate more tracks

Noise and Vibration

  • There will be some noise and vibration due to the construction, but we will use construction methods to minimize these impacts
  • Noise and vibration will be monitored and reported during construction

Tenders

Design consultant: Stantec Consulting
Construction contractor: Not Yet Awarded

 

Highway 27

Project Schedule

  • Design and community consultation to begin soon

What we are doing

  • Add new spans to existing bridge to accommodate more tracks

Noise and Vibration

  • There will be some noise and vibration due to the construction, but we will use construction methods to minimize these impacts
  • Noise and vibration will be monitored and reported during construction

Tenders

Design consultant: Stantec Consulting
Construction contractor: Not Yet Awarded

 

Highway 427

Project Schedule

  • Design Completion: Complete
  • Construction Start: Fall 2011
  • Construction Completion: Summer 2012

What we are doing

  • Building a retaining wall under the bridge at Highway 427 to accommodate two additional tracks
  • This work is phase 1 of the West Corridor Bridge package

How this will affect you

  • The majority of the work will take place during regular construction hours
  • Some construction work may be required outside these hours
  • Advance notice will be provided to the surrounding community when are working outside the regular hours

Noise and Vibration

  • There will be some noise and vibration due to the construction, but we will use construction methods to minimize these impacts
  • Noise and vibration will be monitored and reported during construction

Tenders

Design consultant: Stantec Consulting
Construction contractor: Aecon

How are we doing?

How are we doing?

Tell us what you think of our communications, our public meetings and the information we provide.
Learn more...

Stay in the Know!

Sign up to receive email updates on project information. Subscribe now!

Event Calendar

Check out our Event Calendar to view information about upcoming events.
Find out more...

Contact Us

Georgetown South Project
20 Bay Street, Suite 600
Toronto, ON M5J 2W3
416-406-0489
gts@gotransit.com

Strachan Community Office
901 King Street West, Suite 102
Toronto, ON M5V 3H5
416-581-1300

Weston Community Office
1631 Weston Road
Toronto, ON M9N 1T8
416-241-2300

WTD Community Office
18 Hook Avenue, Suite 204
Toronto, ON M6P 1T4
416-604-9582
By appointment only