West Corridor Bridges
The West Corridor Bridges work package involves widening for railway bridges
in the western portion of the Georgetown South corridor:
Kipling Avenue, Martin Grove Road,
Highway 27 and Highway 427.
Updates
- April 30 – At Highway 427, work on constructing a retaining wall under the bridge continues with the placement of formwork and rebar. We are pouring concrete for the retaining wall facing in sections where the formwork and rebar have already been placed. Once the concrete is strong enough, the formwork will be removed.
This work is expected to be complete by the summer. Phase 2 of the West Corridor Bridge package – which involves widening the bridges at Kipling Avenue, Martin Grove Road and Highway 27 – is expected to start in the summer.
Kipling Avenue
Project Schedule
- Design and community consultation to begin soon
What we are doing
- Add new spans to existing bridge to accommodate more tracks
Noise and Vibration
- There will be some noise and vibration due to the construction, but we
will use construction methods to minimize these impacts
- Noise and vibration will be monitored and reported during construction
Tenders
Design consultant: Stantec Consultingd
Construction contractor: Not Yet Awarded
Martin Grove Road
Project Schedule
- Design and community consultation to begin soon
What we are doing
- Add new spans to existing bridge to accommodate more tracks
Noise and Vibration
- There will be some noise and vibration due to the construction, but we
will use construction methods to minimize these impacts
- Noise and vibration will be monitored and reported during construction
Tenders
Design consultant: Stantec Consulting
Construction contractor: Not Yet Awarded
Highway 27
Project Schedule
- Design and community consultation to begin soon
What we are doing
- Add new spans to existing bridge to accommodate more tracks
Noise and Vibration
- There will be some noise and vibration due to the construction, but we
will use construction methods to minimize these impacts
- Noise and vibration will be monitored and reported during construction
Tenders
Design consultant: Stantec Consulting
Construction contractor: Not Yet Awarded
Highway 427
Project Schedule
- Design Completion: Complete
- Construction Start: Fall 2011
- Construction Completion: Summer 2012
What we are doing
- Building a retaining wall under the bridge at Highway 427 to
accommodate two additional tracks
- This work is phase 1 of the West Corridor Bridge package
How this will affect you
- The majority of the work will take place during regular construction
hours
- Some construction work may be required outside these hours
- Advance notice will be provided to the surrounding community when are
working outside the regular hours
Noise and Vibration
- There will be some noise and vibration due to the construction, but we
will use construction methods to minimize these impacts
- Noise and vibration will be monitored and reported during construction
Tenders
Design consultant: Stantec Consulting
Construction contractor: Aecon