Bypass navigation and go to content
Galt Sub looking West

Weston Tunnel

The GO rail corridor will be lowered from Lawrence Avenue to Weston Road, with a covered portion between King Street and Church Street. Because the rail corridor will not yet have descended low enough to keep the road level, John Street will be closed to vehicular traffic; a pedestrian bridge will be built over the GO tracks to keep John Street open to pedestrians. The corridor will ascend north of Church Street, returning to ground level before the Weston Road bridge.

The Tunnel Cover, between King Street and Church Street, will be at the same grade as the St. John the Evangelist Church and School property lines. With public access from Church or King Street, the tunnel cover is being designed to accommodate a green space and/or recreational public use to be maintained by a third party, such as the City of Toronto or the Toronto Catholic District School Board.

Updates

  • April 30 – On King Street, near George Street, work continues to install an upgraded water main. King Street has been reduced to one lane of traffic westbound to Weston Road from Rosemount Avenue. These restrictions are expected to remain in place through May. Further lane restrictions and closures of King Street will be required in the future, including a closure of the intersection of King Street and Rosemount Avenue. This is required to install a pipe for the new water main.
    Work on Rosemount Avenue has begun between Church and King Streets to upgrade the existing storm sewer. This stretch of Rosemount Avenue will be open to local traffic only. Access to driveways will be maintained throughout the work. North of Church Street, construction of the CP Rail retaining wall is expected to continue until the summer. Hoarding is currently being installed on the west side of the rail corridor.
  • April 20 – CP will be removing and replacing the track panels in the rail crossing at John Street. John Street will be closed at the tracks on Tuesday, April 24 from 6:00 a.m. to 3:00 p.m. For safety reasons, pedestrians will not be able to cross the corridor during these times.
  • April 20 – CP will be removing and replacing the track panels in the rail crossing at King Street. King Street will be closed at the tracks on Wednesday April 25 from 6:00 a.m. to 3:00 p.m. For safety reasons, pedestrians will not be able to cross the corridor during these times. The local schools will need to be accessed from Church Street.

Project Schedule

  • Utility relocation start: April 2011 – June 2011
  • Lawrence Avenue Bridge widening: summer 2011
  • Grade separation construction start: fall 2011
  • Construction complete: end of 2014

What we are doing

  • GO rail corridor will be lowered from Lawrence Avenue to Weston Road, with a covered portion between King Street and Church Street
  • John Street will be closed to vehicular traffic
    • a pedestrian bridge will be built over the GO tracks to keep John Street open to pedestrians

How this will affect you

  • Lane closures on Church Street, between Purdy Crescent and Rosemount Avenue, as we work on the retaining wall on the CP side north of Church
  • Temporary road closures of Church Street and King Street in 2012 or 2013 during tunnel construction
    • Closures will impact only one road at a time
  • Working with property owners for temporary easements to gain construction access

Noise and Vibration

Noise and vibration monitors have been set up along the Weston Tunnel project area to monitor any noise and vibration generated by the construction. This data will be posted on a weekly basis.

The following graph displays 1-hour averaged noise levels measured in decibels (dbA).

Weston Tunnel Noise Monitoring Graph

For a map of the station locations, please click here.

Archived graphs

2011 | January 2-March 31 | April 2-7 | April 9-14 | April 16-21

Vibration

No elevated vibration levels were recorded during this construction period.

Tenders

Design consultant: Delcan
Construction contractor: Phase 1: Avertex
Construction Contractor: Phase 2: Ellis Don
Construction Contractor: Phase 3: KO Contractors

Community Updates

For more information on the Weston Tunnel, please contact the Weston Community Office at 416-241-2300.

How are we doing?

How are we doing?

Tell us what you think of our communications, our public meetings and the information we provide.
Learn more...

Stay in the Know!

Sign up to receive email updates on project information. Subscribe now!

Event Calendar

Check out our Event Calendar to view information about upcoming events.
Find out more...

Contact Us

Georgetown South Project
20 Bay Street, Suite 600
Toronto, ON M5J 2W3
416-406-0489
gts@gotransit.com

Strachan Community Office
901 King Street West, Suite 102
Toronto, ON M5V 3H5
416-581-1300

Weston Community Office
1631 Weston Road
Toronto, ON M9N 1T8
416-241-2300

WTD Community Office
18 Hook Avenue, Suite 204
Toronto, ON M6P 1T4
416-604-9582
By appointment only