We use this space to give you basic information about construction or renovation projects that may be affecting your station or parking lot. This information is as current as possible.
Agincourt GO Station
A portion of the south parking is closed for construction of the new Sheppard LRT. Access to the station building, north lot and remaining parking spaces in the south parking lot will be maintained. For more information on this project, please contact the TTC.
Ajax GO Station
Phase 1 of this project includes preparatory construction of a new west tunnel and future elevator and stairwell enclosures. Approximately 65 parking spaces will be occupied for construction staging. COMPLETION: Phase 1, spring 2010
Appleby GO Station
This project involves construction of elevators, mini-platforms, tunnel and stair rehab, and platform improvements. Approximately, 25 parking spaces in the north lot will be used for construction staging. COMPLETION: March 2010
Aurora GO Station
This project involves construction of a new multi-level parking structure to provide an additional 860 parking spaces north of the existing east lot. Rehabilitation of the station building is currently underway and a new parkette was completed in fall 2009. COMPLETION: March 2010
Brampton GO Station
The project includes the
construction of a new train platform south of the existing tracks, a
new west tunnel, and changes to the existing east tunnel, including
improved pedestrian access and the addition of an elevator.
COMPLETION: April 2010
Burlington GO Station
This project involves the replacement of the four station escalators. In stage 1, the two centre escalators will be replaced with stairs. Once this is completed, the two end escalators will be replaced as well. COMPLETION: April 2010
Clarkson GO Station
This project includes the construction of a new track, pedestrian tunnel with elevators, platform and other improvements. Approximately, 100 parking spaces in the north lot have been relocated for construction staging. COMPLETION: April 2010
Malton GO Station
This project includes a new south platform, west tunnel,
shelters, elevator and staircase from the east tunnel to the centre
platform. COMPLETION: March 2010
Maple GO Station
This project included three phases of parking expansion. All but 50 of the new 929 spaces are available. The 50 occupied spaces are being used for construction staging while improvements to the existing lot and kiss n ride are being made. A new station access road is also being added at Eagle Rock Way. COMPLETION: May 2010
Mount Pleasant GO Station
Access to the north platform from Pleasant Road is restricted due to a municipal project scheduled for completion in spring 2010. GO is currently expanding the parking lot to accommodate approximately 620 cars, as well as a new kiss n ride and pedestrian walkway. Parking spaces will be made available in February 2010 while remaining construction is completed. COMPLETION: June 2010
Oakville GO Station
This project includes the construction of a new north platform and mainline track, as well as a new elevator, stairs, shelters and mini-platform. COMPLETION: May 2010
Upon completion of the station improvements, parking will be expanded.
Pickering GO Station
This project involves a new and improved station building and modifications to the kiss n ride. A covered walkway will connect the west tunnel and bus loop to the new building. The west tunnel escalators will be removed and replaced with stairs. COMPLETION: spring 2011
Whitby GO Station
This project includes the construction of a new pedestrian bridge
connecting the rail platform to the south-east parking lot. A new
bridge will be installed over the south track, as well as elevators
and stairway enclosures. This work requires closing off the east end
of the platform from March 2010 to the fall of 2010 and will
restrict train access to the six west end cars only. COMPLETION:
winter 2010