West Toronto Diamond Grade Separation
West Toronto Diamond Grade Separation
Related pages
Definitions
Canadian Transportation Agency Order
Noise and Vibration Monitoring Log
Community Comments Log
Contacts
Community Updates
Community Status Update -- March 5, 2010
The West Toronto Diamond is part of the Georgetown South Corridor, one of the
most exciting transit projects in the GTA. It will enable a new link from Union
Station to Pearson Airport, and will support expanded service to
Kitchener-Waterloo, Brampton, and Mississauga.
Basically, we are building an underpass to separate two major rail corridors
- right now we have the equivalent of two major highways meeting at a traffic
light. This hurts our ability to provide reliable service for our customers.
We understand that this project has been noisy for some local residents, in
particular, our use of impact hammers to put steel pipes in the ground (known as
piling). In June 2009, we changed the way we were working in order to reduce the
noise, implementing the use of impact hammers equipped with sound mitigation as
well as bringing in quieter piling technology from France and Japan. As a result
of these efforts the noise from our work was cut in half.
In early December, 2009 The Canadian Transportation Agency (CTA) asked for
additional measures, including better information and monitoring of piling
activity. In addition to the earlier measures we implemented in June, we also
incorporated these additional requirements.
Today, we are in full compliance with the CTA's ruling.
Anticipated work plan to the end of May 2010
So far, we have put in 80% of the piles needed for the project, with fewer
than 400 piles to be installed.
During the months of March and April, there are only about 80 piles being
installed. The quiet press-in method will be used for majority of these piles
(about 60). The remainder will be installed using a combination of quieter
equipment including press-in methods and vibratory machines, in combination with
the use of impact hammers equipped with sound mitigation to finish the
installation.
The CTA ruling allows us to use the impact hammers in some circumstances. In
instances where impact hammers are used – including completing the last 10 feet
of a pile which is not possible with the press-in method or vibratory hammer –
we will continue to use sound mitigation measures.
Once work on the outer walls is complete in early May, the track will be
shifted in mid-May to allow the final 320 piles to be installed. Our plan for
work beyond May is being developed and once finalized, that information will be
provided. We will adhere to the CTA ruling on this work as well.
We apologize for the inconvenience this work has caused local residents. We
have and will continue to provide support to the community. If you think this
could help you, or if you have any questions, please contact Kathryn Hanford at
416-604-9582.
We would like to once again thank local residents who have been so
understanding, have worked with us to develop quieter construction methods, and
who like us, want this project completed as quickly as possible. With the CTA
requirements, we hope to complete the piling using the quieter methods by the
end of 2010.
For more information, please see our
contact page.
Project Description
The West Toronto Diamond project will separate Canadian Pacific
Railway's North Toronto freight line from GO's Weston Subdivision
(Georgetown line). The north-south tracks to and from Georgetown will be
lowered so that they run under CPR's North Toronto line.
Improvements
- More reliable GO service by eliminating the need to accommodate
both freight and GO trains at this crossing point.
- Less pollution and noise for residents due to fewer trains
stopping and idling in the neighbourhood, and commuter traffic
running through the lowered corridor.
- Less noise and whistling from trains crossing the West Toronto
Diamond.
- Increased train service for northwest Toronto and Peel Region.
Location: The Junction area in Toronto, where Old
Weston Road cross the rail tracks.
Project Area Map

Legend
G - Giken
I - Impact Hammer
V - PTC Vibro Hammer
M - Moveable Sound Barrier
(#) - Total piles driven each day
Project Schedule
| |
Mon Mar 8 |
Tues
Mar 9 |
Wed Mar 10 |
Thurs Mar11 |
Fri Mar 12 |
Sat Mar 13 |
Sun Mar 14 |
| Zone A |
|
|
|
|
|
No activity |
No activity |
| Zone B |
|
|
|
|
|
| Zone C |
I
V |
I
V |
I
V |
I
V |
I
V |
| Zone D |
I
V
G |
I
V
G |
I
V
G |
I
V
G |
I
V
G |
| |
Mon Mar 15 |
Tues
Mar 16 |
Wed Mar 17 |
Thurs Mar18 |
Fri Mar 19 |
Sat Mar 20 |
Sun Mar 21 |
| Zone A |
|
|
|
|
|
No activity |
No activity |
| Zone B |
|
|
|
|
|
| Zone C |
|
|
|
|
|
| Zone D |
I
V
G |
I
V
G |
I
V
G |
I
V
G |
I
V
G |
| |
Mon Mar 22 |
Tues
Mar 23 |
Wed Mar 24 |
Thurs Mar25 |
Fri Mar 26 |
Sat Mar 27 |
Sun Mar 28 |
| Zone A |
|
|
|
|
|
No activity |
No activity |
| Zone B |
|
|
|
|
|
| Zone C |
I
V |
I
V |
I
V |
I
V |
I
V |
| Zone D |
I
V
G |
I
V
G |
I
V
G |
I
V
G |
I
V
G |
*Shrouded impact hammers will be used to complete piles that cannot
be completed using the other piling methods alone as permitted by the
CTA order. In zones A, B, and C, when impact hammers are used, noise
barriers will be in place. Zone D does not permit the use of noise
barriers as space is restricted.
**Old Weston Road - Pedestrian Road Closure: UPDATE
- Saturday, February 27, 2010, pedestrian access at Old Weston Road has
been re-opened.
Archived Schedules
Project Schedule and Updates: Construction - Phase 2
(piling construction)
Total steel pipe piles driven to date: 1945 of 2338 (391remaining)
GO has implemented several noise mitigation measures to lessen the
impact of the noise from this work on local residents and businesses.
These measures include noise shrouds placed around the machinery and the
installation of moveable sound barriers at the piling site. Since June
8, 2009, GO has voluntarily required that impact hammers, when used,
must be equipped with a noise shroud. The CTA decision placed additional
restrictions on the use of impact hammers effective December 22, 2009.
Impact hammers have not been used at all between December 21 and January
4, 2010, and when work begins again on January 5, shrouded impact
hammers will only be used for the limited use permitted by the CTA
decision.
The noise mitigation measures have been very effective in reducing
the noise disruption, but they have also resulted in a longer
construction schedule for Phase 2 works. The pile installation phase was
originally projected for completion in December 2009, with the
mitigation GO started using in June 2009 and in accordance with the
information previously distributed to the community, the piling contract
would have been extended. It was anticipated last November that the
piling would continue into the summer of 2010 due to the implementation
of these mitigation measures. With the recent decision imposed by the
CTA, piling will now be complete in late 2010. Following this phase of
the project, excavation will occur and the overall project is now
scheduled for completion in the fall of 2014.
Construction hours
The use of the vibratory hammer and impact hammers will be restricted
to the hours of 8:00 a.m. to 4:00 p.m. on weekdays only. Giken
technology may operate between 7:00 a.m. and 7:00 p.m. on weekdays, and
between 9:00 a.m. and 7:00 p.m. on Saturdays.
After December 18th, 2009, the use of impact hammers has been limited
and will be used only in conjunction with a PTC vibratory hammer or only
in exceptional circumstances where no other method is possible.
The CTA decision affects only pile driving activities. Other
construction work that does not include pile driving will generally
occur between 7:00 a.m. and 7:00 p.m. on weekdays, and between 9:00 a.m.
and 7:00 p.m. on Saturdays. On occasion, weekend and/or overnight track
work will be required.