West Toronto Diamond Grade Separation: Canadian Transportation
Agency Order
The CTA decision dictates ways and means of the types of
equipment used for pile driving, how the equipment is used, and when
equipment can be used. These restrictions will dramatically slow the
pace of the work, and the overall project is anticipated to take five
years (to fall 2014) to complete.
In accordance with the CTA decision, GO has restricted the use of
impact hammers and hours of pile driving activity as the December 7,
2009 decision is outlined below:
"Giken Hammer:
- extend the use of the Giken hammer for the duration of the steel
pipe pile-driving activities on the project and for more than the
previously scheduled 250 piles. To that end, GO Transit is required
to pursue an extension of the contract for the use of the Giken
hammer with the supplier for the duration of the pile-driving
activities. If GO Transit is not able to secure an extension to the
contract with the supplier, GO Transit is to notify the Agency, the
WTDCG, and the City of Toronto with an explanation of the reasons
why it was not possible to secure the extension.
- use the Giken hammer in more sensitive areas.
- use the Giken hammer, in addition to weekday pile-driving
activities, for pile-driving activities that take place outside the
standard hours of 8:00 a.m. to 4:00 p.m. on weekdays."
COMMENT: GO is required to pursue an extension
of the contract for the use of Giken. The current piling contract ends
on March 31, 2010 and GO can, through our general contractor, continue
to use Giken. Since September, GO has been using the Giken unit north of
the Old Weston Road crossing, next to the National Rubber Technologies
(NRT) building. Use of the Giken unit has been successful, but its
progress is also very slow. It will take over six months (to the end of
March 2010) to install the 250 piles, about 10 per cent of the total
number of steel pipe piles for this project.
"PTC-Vibro Hammer:
- Within 14 days from the date of this Decision, use a PTC-Vibro
hammer as the primary method to install the steel pipe piles by
augering them, if needed and where possible, to complete their
installation. Where complete installation with a PTC-Vibro hammer
and augering is not possible, drive the piles to the maximum depth
possible, considering soil conditions, with the PTC-Vibro hammer and
only then use an impact hammer to finish the pile-driving
activities. This does not preclude GO Transit from employing a
conventional vibratory hammer in areas that are less sensitive to
vibrations or where GO Transit can mitigate the impact of
vibrations."
COMMENT: As of December 21, the CTA ordered GO
to use the PTC vibratory hammer as the primary method to install steel
pipe piles. This direction is being complied with where possible,
although there are very few of the remaining piles that can be installed
with this equipment. This is because the PTC vibratory hammer often
cannot meet vibration limits set by City of Toronto by-laws or the
restrictive limits set by engineers.
"Impact Hammer and Related Mitigative Measures
- use an impact hammer on the project only in conjunction with a
PTC-Vibro hammer or where no other method is possible.
COMMENT: At a minimum, the impact hammer will
have to be used to install the final one to two metres of the pipe piles
as the PTC vibratory hammer cannot work close to or below ground level.
Previous experience with the PTC vibratory hammer determined that it was
often only able to install the pipe pile as little as halfway.
- where the impact hammer must be used, de-power the impact hammer
and decrease the hammer energy wherever possible and use shrouds,
skirts and rubberized chasers. If shrouds are opened, any opening
must be positioned, wherever possible, down the tracks and not
toward any residential area.
COMMENT: These noise mitigation measures have
been in place since June 8, 2009.
- where the impact hammer must be used, employ moveable noise
barriers, wherever possible, to deflect noise away from nearby
residential areas by moving them to current pile-driving locations."
COMMENT: This is already in place, although
noise barriers can only be used where they do not interfere with worker
safety or train operator sightlines.
"Limited Hours for Pile-Driving Activities
- use the Giken hammer, the preferred method of pile-driving,
between the hours of 7:00 a.m. and 7:00 p.m. on weekdays (excluding
statutory holidays) and between 9:00 a.m. and 7:00 p.m. on
Saturdays.
- restrict the hours of work for installing piles with the PTC-Vibro,
conventional vibratory and impact hammers to between 8:00 a.m. and
4:00 p.m. on weekdays.
- negotiate agreements with the City of Toronto to allow for road
closures such that pile-driving activities undertaken with the PTC-Vibro,
conventional vibratory and impact hammers are limited to between
8:00 a.m. and 4:00 p.m. on weekdays.
- negotiate agreements with other railway companies to allow for
train blocks such that pile-driving activities undertaken with the
PTC-Vibro, conventional vibratory and impact hammers are limited to
between 8:00 a.m. and 4:00 p.m. on weekdays.
- on those exceptional occasions when pile-driving activities must
take place outside of the hours of 8:00 a.m. and 4:00 p.m. on
weekdays and it is not possible to use the Giken hammer, the PTC-Vibro,
conventional vibratory and impact hammers may only be used following
14 days prior notice on GO Transit's Web site of the proposed
activity, including specific details of the constraints that
preclude the use of the Giken hammer. In addition, GO Transit must
report within its communication program the actual use of the PTC-Vibro,
conventional vibratory and impact hammers."
COMMENT: All restrictions as noted in the
limited hours of pile driving activities are being adhered to.
"Noise and Vibration Monitoring
- within 14 days from the date of this Decision, prepare and submit
to the Agency, for approval, a proposed methodology for an enhanced
noise and vibration monitoring program to provide weekly noise and
vibration level measurements, including equipment to be employed,
method of measurement and associated metrics, and the criteria for
selecting the location of measurements.
- at the same time as it submits its proposal to the Agency, provide
copies to the WTDCG and the City of Toronto, which will then have
seven days from receipt of the proposal to submit their comments
regarding the proposed methodology."
COMMENT: The CTA decision required GO to submit
for CTA approval a proposed program for noise and vibration monitoring
by December 22, 2009.
GO has retained the services of a specialist noise and vibration
consultant who provided assistance with the development of the ordered
noise and vibration monitoring program (submitted on December 21, 2009).
The proposal for the terms of reference for this program has been
submitted to the CTA, WTDCG and City of Toronto for review and comment.
Comments were requested for December 29, 2009. As of December 29, 2009,
the Agency has neither approved nor commented on the plan. The City of
Toronto commented on the plan as of December 30.
Once the CTA approves the plan, the implementation of the
required monitoring program will require two to six weeks beyond the
approval of the program as submitted. This is due to the public
tendering process and GOs ability to approve and secure a contract for
the supply and installation of the noise and vibration monitors, the
supply and installation of these monitors, in accordance with and when
the terms of reference that have been agreed to.
The proposal for the terms of reference for this program has been
submitted to the CTA, WTDCG and City of Toronto for review and comment.
Comments were requested for December 29, 2009.
"Communications
- within 7 days from the date of this Decision, post on the current
Web site and update daily all scheduled pile-driving activities for
the project and their location, as well as any scheduled periods of
inactivity (project plans) for a projected period of no less than 14
days from the date of posting, which project plans cannot be changed
except following notice as set out in c) below.
COMMENT: Implemented on December 14, 2009.
- within 28 days from the date of this Decision, consult with the
WTDCG and the City of Toronto, and implement, a more comprehensive
communication program, which must include:
- an enhanced Web site, which is updated daily, to communicate
information to local residents and businesses including, without
limitation, detailed information about the current pile-driving
activities and associated equipment on the site; the project plans
for a projected period of no less than 14 days from the date of
posting, which project plans which cannot be changed except
following notice as set out in c) below; and, the locations and
projected locations of moveable barriers and any constraints that
preclude the use of moveable barriers at any location; and
- an e-mail address and phone line, both to be answered by a person
knowledgeable about the project and its schedule, for residents and
businesses to communicate particular concerns about the current and
projected pile-driving activities and to which GO Transit must
investigate and respond within 48 hours.
COMMENT: Implemented on January 5, 2010 with
input received from the City of Toronto and individual community
members, but not the WTDCG.
- in the event of exceptional circumstances which necessitate a
temporary change in the project plans and prior to such change being
implemented, GO Transit is to post such change on the current, and
thereafter the enhanced, Web site, together with the anticipated
duration of the change and the reasons necessitating the change; and
if required, revise the project plans to reflect such change.
- within 14 days following the approval by the Agency of the noise
and vibration monitoring methodology, commence posting on the Web
site a weekly report containing the results of noise and vibration
measurements as well as an assessment of the effectiveness of
implemented mitigative measures; and, subject to compliance with
privacy protection legislation, any complaints received, and how
they were addressed and resolved."
COMMENT: Posting of complaints information is
implemented and an update on the status of the noise and vibration
monitoring program has been provided on January 4, 2010.
For a summary of the complete Canadian Transportation Agency Order of
Specific Corrective Measures, please see the CTA website posting.