West Toronto Diamond Grade Separation: Definitions
Interlocking steel pipe piles: Pipe piles make up
the majority of the piles required for the West Toronto Grade
Separation. They provide the structural strength and the required water
tightness for the walls that will make up the structure for the lowered
track section.
Impact hammers: Impact hammers are the fastest, most
effective and reliable means of installing pipe piles. They provide a
high level of accuracy, which is important because of the tight corridor
dimensions and surrounding operational tracks. Impact hammers are also
the noisiest.
(Conventional) vibratory hammers: In the industry,
vibratory hammers are currently mostly used to remove piles out of
alignment and/or temporary piles, but can also be used for pile driving.
Vibratory hammers use vibration rather than impact to advance the pile;
therefore, they have more difficulty getting through dense soil
conditions at depth. Vibratory hammers are also less accurate with the
sites soil conditions and depths of piles required for this project.
Vibratory hammers do produce less noise; however, the vibration they
produce is constant and can be unsettling to residents of the
neighbourhood. The vibration levels produced by the vibratory hammer are
also more difficult to control. For these reasons, the conventional
vibratory hammer is only used for pre-work setup, and has not ever been
used on the project for actual pile installation.
Computer-controlled (French or PTC) vibratory hammer:A
unique computer-controlled vibratory hammer was brought in from Europe
for this project. This machine allows much greater control of vibration
levels, although when in use has caused some disruption in the
neighbourhood. Progress with the machine has been slow, and often it has
not been able to fully drive piles to the required depth.
Giken unit (or technology): This technology uses a
hydraulic press-in method. The machine is one of two in the world with
sufficient capacity to install the size of piles required for this
project. The Giken unit has some significant limitations. The machine
was brought in from Japan and was untested in the type of soil
conditions at this site. With a maximum production rate of up to two
piles per day, the project schedule will be significantly extended.
Shrouds: Hydraulically operated enclosures around
the impact hammer that muffle the noise from the hammer impacting the
pile, and the hammer itself. The shrouds are made using special sound
absorbing material resistant to high temperatures, and were custom
developed and fabricated for this project.
Noise walls: Sections of sound absorbing noise
barrier (used along highways) mounted on a moveable frame.
Depowering of the impact hammer: Reducing the power
produced by the hammer to soften the blow.This reduces the noise level
by up to 10 decibels (50 per cent), but increases the number of blows
needed to install the pile.