Aldershot GO Station
|
|
|
Due to station renovations, the elevators are not operational. Passengers using mobility aids are advised to use the Burlington GO Station. This work is scheduled to be completed by July 2008.
|
Aurora Carpool Lot (Aurora Rd. & Hwy. 404)
|
|
|
Construction of a bus loop with a multi-bay platform, installation of a bus shelter, and asphalt paving are scheduled to be completed by the end of May 2008.
|
Brampton GO Station
|
|
|
Construction has started on a south platform, a west pedestrian tunnel, and modifications to the existing east tunnel.
|
Bronte Carpool Lot (Bronte Rd. & Hwy. 407)
|
|
|
Construction of a parking lot, bus loop facility, and bus shelter are scheduled to begin soon.
|
Burlington GO Station
|
|
|
Construction of a multi-level parking structure is scheduled to be completed by the end of June 2008.
|
Danforth GO Station
|
|
|
Construction of a third track and station improvements are scheduled to be completed by the end of June 2008.
|
Erindale GO Station
|
|
|
Mini-platform construction expected to be complete Spring 2008. During construction, all trains will be operating from the east track (closest to the building), rather than the usual west track.
|
Finch GO Bus Terminal
|
|
|
Asphalt rehabilitation in bus turnaround loop will start summer 2008.
|
Hamilton GO Centre
|
|
|
Ticket sales area renovation project expected to be complete end of June 2008. For the duration of the work, tickets can be purchased at the trailer, located outside the concourse area, on the west side of the station building facing James St.
|
King City GO Station
|
|
|
Parking Lot Expansion: The construction of approximately 250 additional parking spaces is scheduled for completion in May 2008.
|
Maple (Major Mackenzie & Hwy. 400)
|
|
|
Construction of a bus platform and bus shelter is ongoing.
|
Maple GO Station
|
|
|
Construction will start soon on expansion and modifications to the existing parking lot.
|
Meadowvale GO Station
|
|
|
Tunnel and elevator installation is scheduled to be completed by the end of September 2008.
|
Mount Pleasant GO Station
|
|
|
Construction of a new island platform, with stair and elevator access from both the east and west ends of the existing station tunnel, is scheduled to be completed by the end of December 2008.
|
Newmarket Carpool Lot (Hwy. 9 & Hwy. 400)
|
|
|
Construction of a replacement bus shelter is ongoing.
|
Oakville Carpool Lot (Trafalgar Rd. & Hwy 407)
|
|
|
Construction of a parking lot, bus loop facility, and bus shelter are scheduled to begin soon.
|
Oriole GO Station
|
|
|
Platform extension construction and the addition of two (2) platform shelters are scheduled to be completed by the end of June 2008.
|
Richmond Hill GO Station
|
|
|
Parking Expansion: is substantially complete. Additional paving will be completed Spring 2008.
|
Scarborough GO Station
|
|
|
The construction of a new tunnel to the north platform, platform shelters and the addition of elevators that will make the station accessible is expected to be complete by the Summer of 2009.
|
Stouffville GO Station
|
|
|
Platform extension construction, the addition of a platform shelter, and parking lot improvements are scheduled to be completed by the end of December 2008.
|
Streetsville GO Station
|
|
|
Construction that consists of the installation of a new tunnel and the extension of the train platform to accommodate 12-car trains is scheduled to be completed by the end of October 2008.
|
Union Station
|
|
|
Front St. access may be restricted due to TTC construction project. Expected completion date is Nov. 2007. Construction of a new platform number 13/14 is scheduled for completion Spring 2008.
|