Agincourt GO Station
|
|
|
A portion of the south parking lot will be closed effective October 11, 2009 for construction of the new Sheppard LRT. Access to the Station Building, north lot and remaining parking spaces in the south parking lot will be maintained.
|
Ajax GO Station
|
|
|
Completion Date:Phase 1, December 2009 Phase 1 of this project includes preparatory construction of a new west tunnel and future elevator and stairwell enclosures. Approximately 65 parking spaces will be lost to the staging of construction equipment.
|
Appleby GO Station
|
|
|
COMPLETION DATE: March 2010 This project involves construction of elevators, mini-platforms, tunnel and stair rehab, and platform improvements. 25 north lot parking spots will be unavailable, and reserved and accessible parking will be moved.
|
Aurora GO Station
|
|
|
Completion date: March 2010 This project involves construction of a new multi-level parking structure which provide an additional 860 parking spaces north of the existing east lot as well as rehabilitation of the station building and a new parkette.
|
Brampton GO Station
|
|
|
COMPLETION DATE: November 2009 This project involves a new platform south of the existing tracks, as well as a new west tunnel. Also, improvements to the existing east tunnel will include pedestrian and elevator access to both platforms
|
Bronte GO Station
|
|
|
Completion date: December 2009 This project involves expansion of the existing gravel parking lot to Wyecroft Rd with an additional 370 parking spaces, including asphalt paving, lighting, signage, fencing and landscaping.
|
Centennial GO Station
|
|
|
Completion date: November 6, 2009 Due to electrical transformer work by the Town of Markham, a row of parking spaces in the northeast of the lot will be temporarily unavailable, however two temporary rows will be provided in its place.
|
Clarkson GO Station
|
|
|
COMPLETION DATE: December 2009 This project includes the construction of a new track, pedestrian tunnel with elevators, platform and other improvements. There will be a loss of 100 parking spots in the north lot and accessible parking will be moved.
|
Cooksville GO Station
|
|
|
Completion date:February 2010 This project includes rehabilitation of existing bus platforms and the parking lot directly south. Improvements will also take place on the wooden curbs adjacent to the station building.
|
Malton GO Station
|
|
|
COMPLETION DATE: February 2010 This project includes a new south platform, west tunnel, shelters, elevator & staircase from the east tunnel to the centre platform. Some parking spaces will be occupied and accessible spaces will be relocated.
|
Maple (Major Mackenzie & Hwy. 400)
|
|
|
Completion date: mid-November 2009 This project includes the installation of one covered bicycle shelter which will accommodate approximately 20 bicycles.
|
Maple GO Station
|
|
|
Completion date:December 2009 We've added 280 parking spaces effective September 28. Work continues to add additional spaces, new internal roads and changes to the existing lot and kiss & ride that will allow a total of 929 spaces.
|
Mount Pleasant GO Station
|
|
|
Completion date: Winter 2010 Construction of a new parking lot to accommodate 700 cars at the west end of the station, landscaping, a new kiss-&-ride, paving, pedestrian walkway and lighting.
|
Oakville GO Station
|
|
|
COMPLETION DATE: December 2009 This project includes a new north platform and mainline track, new elevator and stair structures, new shelters and mini-platform. Additional parking spaces will be provided once the work is complete.
|
Oriole GO Station
|
|
|
Completion date: mid-December 2009 This project involves pedestrian bridge rehabilitation including new stairs with non-slip surfaces, improved lighting, rust removal and painting. Temporary bridge closures may be required outside of rush hours.
|
Pickering GO Station
|
|
|
Completion date:Spring 2011 This project involves a new & improved station building and modifications to the Kiss & Ride. A covered walkway will connect the west tunnel & bus loop to the new building, and the west tunnel escalators will be removed.
|
Port Credit GO Station
|
|
|
Completion date: December 2009 This project involves re-aligning the existing tracks as well as the island platform to accommodate the construction and connection of a third track. 20 parking spaces in the southwest lot will be temporarily blocked.
|
Rouge Hill GO Station
|
|
|
Completion date: October 2010 This project includes a new parking lot for 327 vehicles, an access road linking the existing south lot to the new lot, full rehabilitation of the north lot and minor upgrades to the south lot.
|
Scarborough GO Station
|
|
|
COMPLETION DATE: November 2009 This project involves the construction of a new tunnel to the north platform, platform shelters and the addition of elevators that will make the station accessible.
|
Union Station
|
|
|
Completion date: Fall 2009 This project involves the installation of staircases which will provide direct platform access to Platforms 3-9 from new Bay West Teamway entrances to the GO Concourse.
|
Unionville GO Station
|
|
|
Completion Date: early November 2009 This project includes new parking for 300 vehicles, with an access road linking it to YMCA Bl. It will have an asphalt surface, lighting, concrete curbs, drainage system, landscaping and CCTV.
|
Whitby GO Station
|
|
|
COMPLETION DATE: December 2009 This project involves the construction of a multi-level parking structure which will provide an additional 900 parking spaces in the south parking lot, and the accessible parking spaces will be temporarily relocated.
|
Yorkdale Bus Terminal
|
|
|
Completion date: end of December 2009 This project consists of rehabilitation of the heated bus ramp system at the terminal.
|