Track Improvements
Upgrades to the tracks will improve reliability and efficiency of
train operations.
When the track layout around Union Station was designed, the emphasis
was on moving intercity long-distance passenger trains and freight.
Those requirements have largely been replaced by the need to move
commuters in and out of downtown Toronto. While the total number of
station tracks will remain the same, tracks are being reconfigured to
reduce the amount of switching between tracks.
As part of the renewal program, track and switches are being upgraded
to increase reliability and allow faster train speeds on the approaches
to Union Station. There are over 100 switches which are being replaced
over a six year period, with 2012 being the final year of the program.
The installation and testing of a single switch is an around-the-clock
operation, started after the Friday night rush and ending just before
the Monday morning operations start up.
New track in the “fly-under” west of Union Station
The main objective of this project is to build a third main track
through the fly-under (tunnel) west of Union Station, providing an
additional route from the Georgetown and Lakeshore West corridors
through to Union Station. This will give us added capacity on the west
approach to Union Station for growth in train service, provide more
routing options, and help to lessen the impact of train delays.
Construction of the new, third track will require new retaining walls
leading to the fly-under, along with grading and drainage work. This
work started in April 2010.
Click
here for a copy of the most current Community Update.
CURRENT STATUS: January 2012
- Wall construction is complete
- Track-related construction (Union Station west to Bathurst
Street) continues
PROJECT TIMELINE
- Construction Started: Spring 2010
- Overall Target Completion Date: Summer 2012
Track Improvements: Switch Replacement
There are about 100 track switches that need to be replaced in the
Union Station Rail Corridor. New switches will allow trains to run
faster into and out of Union Station giving us options to add more
service as ridership increases.
Track switches move trains from one track to the next, allowing an
approaching train to take either one route or the other. Some of the
switches around Union Station have more complicated designs; these are
called Double Slip Switches. Switch replacement is a complex process
involving advance planning and preparatory work, installation, and
testing. The installation and testing of a single switch is an around
the clock operation, starting after the Friday rush and ending just
before the Monday morning operations start up.
Speeds through the double slip switches are limited to 25 km per
hour. After the switches are replaced, we will see speeds of 50 to 70 km
per hour.
This work on the track switches is being done over a six-year period.
Crews are working at night and on weekends to minimize disruption to GO
Train service.
CURRENT STATUS: July 2011
- Double Slip Switch (DSS) replacement program is 85% complete
PROJECT TIMELINE
- Of the 100 locations where switches need to be
replaced, nine locations were completed during
construction season in 2006, 22 in 2007, 18 in 2008, 23
in 2009, 17 in 2010 and 16 are scheduled for 2011
- Major work at Cherry Street was finished during the
summer of 2009, in advance of the signal modernization
work planned for this area
- Overall Target Completion Dated: November 2012